Leanora Line Weld Defect Removal

Leanora Line

Our Projects /

Leanora Line Weld Defect Removal

Key Information

Leanora Line Weld Defect Removal

Project Name
Leanora Line Weld Defect Removal
Client Name
ARC Infrastructure
Location
Kalgoorlie
Duration
2-3 Months

Objective

LGC Rail Services was appointed by ARC Infrastructure to remove and replace defective rail welds along the Leanora Line to restore track integrity and ensure ongoing rail safety and performance. 

Scope of Works

Our scope included the supply of labour, equipment and materials to remove defective rail welds. This included: 

Project Outcome

The project was completed with a 2-3 month timeframe, delivering a fully restored section of the track with all defective welds removed and replaced. The upgraded rail sections met required safety and performance standards, ensuring improved track reliability and longevity.

Get in touch with our team to discuss your requirements and see how we can support your next project.  

Get in Touch

Reliable Solutions,
Ready to Help

Our team is happy to assist with any questions you have. Please contact us via phone or email, or complete the contact form provided, and we’ll be in touch promptly.

26 Bulbey Street,
Bellevue WA 6056

Send a message

Your Name(Required)

BILO Lighting Upgrade

BILO Lighting

Our Projects /

BHP BILO Lighting Upgrade

Key Information

BHP BILO Lighting Upgrade

Project Name
BILO Lighting Upgrade
Client Name
BHP Rail Engineering
Location
Nelson Point, Port Hedland
Duration
3 Months

Objective

BHP engaged LGC Rail Services to upgrade and install new lighting infrastructure at key operational areas at BHP BILO Crossing Nelson Point.

The project was aimed at improving safety and operational visibility across the crossing, ensuring compliance with strict site standards and enhancing conditions for both day and night operations.

Scope of Works

The project required the installation of three new light poles at strategic locations across the BILO crossing. Works involved a range of civil construction works delivered in collaboration with rail and road operations to minimise disruption.

Safety & Performance

Safety and performance were key to project delivery. Our team worked collaboratively with BHP to meet all compliance requirements while maintaining efficiency across site activities.

Project Outcome

The upgraded lighting infrastructure has significantly improved visibility and safety across the BILO crossing. With seamless coordination, careful planning and safe execution, the project was delivered to the client’s satisfaction and has enhanced operational reliability at BILO Crossing Nelson Point.

Get in touch with our team to discuss your requirements and see how we can support your next project.  

Get in Touch

Reliable Solutions,
Ready to Help

Our team is happy to assist with any questions you have. Please contact us via phone or email, or complete the contact form provided, and we’ll be in touch promptly.

26 Bulbey Street,
Bellevue WA 6056

Send a message

Your Name(Required)

Midland Junction Alliance

Midland Junction Alliance

Our Projects /

Midland Junction Alliance

Key Information

Midland Junction Alliance

Project Name
Midland Junction Alliance
Client Name
MGC Solutions
Location
Midland
Duration
8 Months

Objective

As part of the Metronet Midland Station Upgrade, LGC Rail Services was engaged by MGC Solutions through the Midland Junction Alliance (MJA) to deliver the installation of Rail Signalling assets.

The objective of the project was to support the removal of the arc loop and modernise the signalling system with minimal disruption to network operations.

Scope of Works

Our team supplied all labour, equipment and materials required for the installation of the rail signalling infrastructure.

This included:

Project Outcome

The project was delivered on time and to a high standard, with all rail signalling assets installed and completed within an 8 month timeframe. Integration with existing systems was seamless and all works met required safety and performance standards.

Get in touch with our team to discuss your requirements and see how we can support your next project.  

Get in Touch

Reliable Solutions,
Ready to Help

Our team is happy to assist with any questions you have. Please contact us via phone or email, or complete the contact form provided, and we’ll be in touch promptly.

26 Bulbey Street,
Bellevue WA 6056

Send a message

Your Name(Required)

Rail Technology Programme

Rail Technology Programme

Our Projects /

Rail Technology Programme

Key Information

Rail Technology Programme

Project Name
Rail Technology Programme
Client Name
Wabtec
Location
Port Hedland to Newman
Duration
12+ Months

Objective

LGC Rail Services was engaged to support Wabtec in the delivery of the Rail Technology Programme (RTP) from Port Hedland to Newman. 

The project aimed to upgrade and modernise rail control systems, improve operational efficiency and enhance network safety across one of Western Australia’s key freight corridors.

Scope of Works

As part of the project, LGC Rail Services provided a comprehensive supply of labour hire and equipment to assist with the construction works for the RTP project.

Our team supported Wabtec’s control systems division in delivering critical works across the project. Roles supplied included labourers, operators, electrical trade assistants, electricians, leading hands, supervisors, superintendents, HSE personnel and administrative staff.

These resources were integral to maintaining project momentum and ensuring consistent delivery across remote and logistically challenging environments.

Project Outcome

Over the 12+ month period, our workforce played a vital role in assisting Wabtec in completing the project, by supplying experienced labour hire to ensure works were delivered safely, efficiently and to the highest standards. The collaboration highlighted LGC Rail’s capability to support large-scale rail technology projects in regional locations across Western Australia.

Get in touch with our team to discuss your requirements and see how we can support your next project.  

Get in Touch

Reliable Solutions,
Ready to Help

Our team is happy to assist with any questions you have. Please contact us via phone or email, or complete the contact form provided, and we’ll be in touch promptly.

26 Bulbey Street,
Bellevue WA 6056

Send a message

Your Name(Required)

Thornlie-Cockburn Link (TCL)

Thornlie-Cockburn Link

Our Projects /

Thornlie-Cockburn Link

Key Information

Thornlie-Cockburn Link (TCL)

Project name
Thornlie-Cockburn Link (TCL)
Client name
NEWest Alliance
Location
Thornlie Cockburn
Duration
12 months

Objective

LGC Rail Services was contracted by NEWest Alliance to support the construction of the new Thornlie-Cockburn Link by supplying labour hire, equipment and materials for the installation of rail signalling assets. 

The Thornlie-Cockburn Link is a major METRONET project that connects the Mandurah and Armadale Lines to create Perth’s first east-west rail line connection. 

Officially opening in June 2025, the overall project involved the construction of 17.5km of new rail line and two new stations, reducing travel times and making public transport easily accessible for residents in Perth’s south-eastern suburbs.

Scope of Works

Our scope included the supply of labour, equipment and materials to carry out key signalling works along the new rail line.

Project Outcome

The project was successfully delivered over a 12 month period, with all works completed with zero punchlist items, reflecting our team’s experience, capability and quality of work in delivering rail signalling services across Perth’s Public Transport Network.

Get in touch with our team to discuss your requirements and see how we can support your next project.  

Get in Touch

Reliable Solutions,
Ready to Help

Our team is happy to assist with any questions you have. Please contact us via phone or email, or complete the contact form provided, and we’ll be in touch promptly.

26 Bulbey Street,
Bellevue WA 6056

Send a message

Your Name(Required)