Leanora Line Weld Defect Removal
Our Projects /
Leanora Line Weld Defect Removal
Key Information
Leanora Line Weld Defect Removal
Project Name
Leanora Line Weld Defect Removal
Client Name
ARC Infrastructure
Location
Kalgoorlie
Duration
2-3 Months
Objective
LGC Rail Services was appointed by ARC Infrastructure to remove and replace defective rail welds along the Leanora Line to restore track integrity and ensure ongoing rail safety and performance.
Scope of Works
Our scope included the supply of labour, equipment and materials to remove defective rail welds. This included:
- Cutting of rail plugs 8m
- Cutting of defect welds out of track
- Replacing rail with 8m plug
- Welding of the replacement 8m rail plugs
- Profile grinding of welds
- Clipping up rail
Project Outcome
The project was completed with a 2-3 month timeframe, delivering a fully restored section of the track with all defective welds removed and replaced. The upgraded rail sections met required safety and performance standards, ensuring improved track reliability and longevity.
Get in touch with our team to discuss your requirements and see how we can support your next project.
Get in Touch
Reliable Solutions, Ready to Help
Our team is happy to assist with any questions you have. Please contact us via phone or email, or complete the contact form provided, and we’ll be in touch promptly.