Objective

As part of the Metronet Midland Station Upgrade, LGC Rail Services was engaged by MGC Solutions through the Midland Junction Alliance (MJA) to deliver the installation of Rail Signalling assets.

The objective of the project was to support the removal of the arc loop and modernise the signalling system with minimal disruption to network operations.

Scope of Works

Our team supplied all labour, equipment and materials required for the installation of the rail signalling infrastructure.

This included:

Project Outcome

The project was delivered on time and to a high standard, with all rail signalling assets installed and completed within an 8 month timeframe. Integration with existing systems was seamless and all works met required safety and performance standards.

Get in touch with our team to discuss your requirements and see how we can support your next project.  

Get in Touch

Reliable Solutions,
Ready to Help

Our team is happy to assist with any questions you have. Please contact us via phone or email, or complete the contact form provided, and we’ll be in touch promptly.

26 Bulbey Street,
Bellevue WA 6056

Send a message

Your Name(Required)